Every Phase 1 project type for West Hollywood, in one place.
Permit office: West Hollywood Community Development — Building & Safety.
Plan-check timeline: 6–10 weeks typical residential; design review adds 4–8 weeks for façade changes.
Distinctive overlays: Rent Stabilization Ordinance (any added rental unit including ADUs is subject to RSO), Eastside / R1A small-lot requirements, Norma Triangle and Tri-West historic survey areas, Sunset Strip Specific Plan.
Fee load: ~5–7% of valuation.
RSO interaction is unique enough that ADUs on parcels with existing RSO units fall under rent-stabilization once rented — the only city in the matrix where this is true.